海上平台开式排放系统流程优化改造探讨与实施

郭奕杉, 李耀全, 温振栋, 程涛, 于立欣   

  1. 中海石油(中国)有限公司蓬勃作业公司 天津 300459
  • 收稿日期:2023-04-07 出版日期:2023-04-25 发布日期:2023-12-27

Discussion and Practice on Process Optimization and Transformation of Offshore Platform Open Drain System

GUO Yishan, LI Yaoquan, WEN Zhendong, CHENG Tao, YU Lixin   

  1. Pengbo Operation Company,CNOOC <China> Co.,Ltd.,Tianjin 300459,China
  • Received:2023-04-07 Online:2023-04-25 Published:2023-12-27

摘要: 溢油事故是海上平台比较严重的突发事件,在平台生产过程中应全面消除可能发生的溢油隐患。渤海某海上平台共有2个开排槽,来液包括雨雪水及含有油污和化学药剂的有毒害液体。平台ODP设计中开排槽没有安装液位监测设备,投产使用后,中控人员无法对其液位进行有效监控,只能通过定时巡检观察液位并启动气动隔膜泵将开排槽内介质转入开排罐中,如遇暴雨等突发情况导致开排槽液位迅速上涨,将无法确保设备液位及时受控,存在发生溢油入海的隐患。针对此种情况,平台生产人员自主安装开排槽液位开关、加装防溢油升高堰板,实施了开排槽介质转入开排罐和污油罐双流程改造,并完成了气动隔膜泵换泵工作。优化改造后实现了开排槽液位的及时监控,消除了溢油隐患,取得了良好的环境效益和经济效益。

关键词: 海上平台, 开排系统, 开排槽, 流程改造, 溢油风险

Abstract: Oil spill accident is a serious emergency of offshore platform. The potential oil spill hidden danger should be eliminated in the process of platform production. An offshore platform in the Bohai Sea has two open drain sumps,collecting rain and snow water and toxic liquids containing oil and chemical agents. There is no liquid level monitoring device installed in the open drain sumps of the platform ODP design. After they are put into operation,the central control personnel cannot effectively monitor the liquid level. They can only observe the liquid level through regular inspection and start the pneumatic diaphragm pump to transfer the medium from the open drain sumps to the open drain tanks. If the liquid levels in the open drain sumps rise rapidly due to unexpected circumstances such as heavy rain,the liquid level of the equipment cannot be controlled in time,and there is a risk of oil spill into the sea. In view of this situation,the production personnel of the platform independently installed the level switches of the open drain sumps,installed the raising weir plates to prevent oil spill,carried out the double process transformation of the medium from the open drain sumps to the open drain tank and the dirty oil tank,and completed the work of changing the pump of the pneumatic diaphragm pump. The optimized process realized the timely monitoring of the liquid levels in the open drain sumps,eliminated the potential oil spill,and achieved good environmental and economic benefits.

Key words: offshore platform, open drain system, open drain sump, process transformation, oil spill risk